Accelerate your fiber broadband deployments with this expert advice

Starting a new fiber project is often daunting. And fiber networks all have unique challenges. So Clearfield compiled five key tips to make your installations smoother, future-proof, and as fast as possible.

1. Who gets the FTTH services?

You need to start by knowing your network environment. Then consider its present and future needs. Because of 5G and next-gen wireless, network planners should investigate more than how to provide fiber to the home (FTTH) in the serving area. They should also explore how to include businesses, DAS sites, Small Cells, and other locations associated with 5G and converged telecom networks.

This can be a little intimidating. However, categorizing these locations as “just another home” makes things less complicated. Networks incorporate connections. What these connections do is not very important because each of them needs the same basic things. That’s why we often refer to them as fiber to anywhere (FTTx).

2. What kind of fiber drop do I need?

Fiber drops are often the least considered, but the most complicated, part of the FTTH/FTTx network design because each home or business (or cell site) is different. The old way of just placing a flat drop to a home or business may not be the best solution anymore. Because data usage is growing at such a rapid pace, planners need to build multiple pathways to prospective client locations.

By building a pathway (or duct structure), they can ensure that no matter the broadband appetite for that particular site, they can provide it. Single fiber, multi-fiber, and connectorized fibers are accommodated by a single duct. For a future service upgrade, single fibers can easily be replaced with a multiple fiber drop because the pathway is already in place.

3. Should I splice fiber optics?

Pre-connectorized drops are competing with spliced drops. A big reason is the shortage of skilled labor, which will only get worse with the hyper-densification of 5G and 6G. Because of the sheer number of sites, splicing at every network location is very time consuming in FTTH/FTTx networks.

In a typical splicing scenario, the splicer:

  • Arrives at the location to splice the drop

  • Unloads the splicing equipment

  • Goes to the first end

  • Prepares the fiber (removes the sheath, cleans and cleaves)

  • Splices the fiber

That’s one end. The total time for these operations to be completed is about 20 minutes.

Now the splicer goes to the other end and:

  • Prepares the fiber (removes the sheath, cleans and cleaves)

  • Splices the fiber

  • Cleans up tools and loads them back into the vehicle

This operation takes about 10-15 minutes, for a total of 30-45 minutes per location.

In the same scenario, but using a pre-connectorized drop, the splicer:

  • Arrives at the location to connect the drop

  • Gets out of the vehicle

  • Snaps two housings on the pre-connectorized fiber drop

These operations take about 10-15 seconds; we’ll round up to 5 minutes.

Now the splicer goes to the other end and:

  • Plugs the fiber into the bulkhead (since it’s already pre-connectorized)

This operation takes under 1 minute; we’ll round up to 5 minutes.

Although these operations actually take about 2 minutes total, we’ll round up to 10 minutes total.

Result of splicing fiber vs. pre-connectorized drops:

30-45 minutes per location (to splice) vs. 10 minutes per location (using pre-connectorized drops).

20-35 minutes are saved per location by using pre-connectorized drops!

If we calculate a 1,000-location deployment, this equates to a total of 20,000 to 35,000 minutes of time savings — which equates to 333-583 hours saved over the total build. When applied to a technician’s average loaded hourly rate of $100/hour, the planner can recognize a cost savings of $33,000-$58,000. For operators on tight budgets, the savings from plug-and-play network solutions are nothing to bat an eye at.

4. What about network maintenance?

Maintenance is sometimes overlooked at the planning phase of the FTTH/FTTx deployment, but that can come back to haunt you. Planning for the inevitable cut of a fiber feeding a home, business, or wireless location and deploying products that allow for easy restoral can pay great dividends when a cut occurs. As the saying goes, “It’s not a matter of if — it’s a matter of when.”

In FTTH/FTTx networks, the most vulnerable piece is usually the final drop. Planning for this eventually can reduce the pains for both the provider and the end-user. It also provides an added benefit of network upgrades without costly overbuilding.

Ducted drop solutions achieve these two goals. By placing a ducted drop solution using a CIC (Cable in Conduit) or separate components of fiber and duct, the ability to quickly restore the service that is damaged — as well as the ability to upgrade drops from single to multiple fibers — is as simple as repairing the pathway and placing a new fiber drop. In most cases, the repair can be done in hours instead of days. If your customer is a business or possibly a cell site, time matters. An added benefit is a single truck roll (rather than multiple truck rolls) can repair the damage.

5. How do I accommodate growth?

When planning FTTH/FTTx networks, it is important to size for the next decade. It is very hard to predict what exactly will be needed in your network 5-10 years from now. However, it is possible to build in some reasonable facilities for growth, especially in the three most common areas: residential, commercial, and wireless.

The best way to prepare without stranding network assets is to approach the design from a modular perspective. Consider this. Clearfield traditional FDH (fiber distribution hub) cabinets come fully populated with a stub cable for splicing. For example, the FieldSmart® Cabinet line using the Clearview ® cassette allows the planner to deploy the cabinet into the network in a modular fashion without having it fully populated, then adding cassettes as facilities are needed.

For instance, one typical scenario we often hear about is where the Outside Plant Engineer knows the following:

  • The fiber distribution area, when fully developed, needs 288 ports of connectivity.

  • The project will be completed over multiple years.

  • During the first year, only 144 ports are needed.

With the above information, the network planner can call for a FieldSmart 288 cabinet and 12 Clearview cassettes initially (each cassette has 12 ports). Since the splicing is done inside the cassettes, the backhaul fibers can be brought directly into the cabinet and spliced. As the development grows, additional cassettes can be added and spliced into the backhaul as needed. This results in savings because:

  • Only the fiber that is needed at the time of activation is brought into the cabinet.

  • By splicing inside the cabinet, an extra splice case and a hand hole to house it are not needed, eliminating the cost to install both.

Using this approach, backhaul fiber is not deployed until it is required, and the cost of the cabinet can be prorated to match growth in the area. That way, even if the project takes many years to complete, those fiber assets and ports are not stranded.

As you look at network design, keep these five tips in mind. If you have any other questions about your fiber project, remember that we have tons of experience with FTTH/FTTx network designs and installations and are happy to help.

Ready to optimize your FTTH/FTTx deployments? Clearfield can help.

This Website Uses Cookies

We use cookies to provide our services, to allow us to better understand our audience, and to provide and serve personalized ads or content. You can read more about our information collection in our Privacy Policy.

Close

Customize Consent Preferences

As detailed in our Privacy Policy, we use cookies or other technology that may be considered sales, sharing, or targeted advertising under certain privacy laws. You can select your preferences for optional cookies by using the checkboxes below.

These cookies are required for the operation of our sites and enable you to navigate the sites and their features.

These cookies are used to recognize you when you return to the sites and these cookies facilitate measurement and analytics for improved browsing experience.

These cookies, beacons, and pixels allow us to analyze activities on our sites. They can be used to improve the functioning of the sites. For example, these recognize and count the number of visitors and see how they move around the sites. These also help us measure the performance of and optimize the content on the site.

These cookies and pixels are used to deliver relevant ads, track ad campaign performance, or track email marketing.